This notebook demonstrates the Critical Path Method using GLPK/MathProg.
The Critical Path Method is a technique for calculating the shortest time span needed to complete a series of tasks. The tasks are represented by nodes, each labelled with the duration. The precedence order of the task is given by a set of arcs.
Here we demonstrate the representation and calculation of the critical path. Decision variables are introduced for
Tasks on the Critical Path have zero slack.
%%writefile ProjectCPM.mod
# Example: ProjectCPM.mod
set TASKS;
set ARCS within {TASKS cross TASKS};
/* Parameters are the durations for each task */
param dur{TASKS} >= 0;
param desc{TASKS} symbolic;
/* Decision Variables associated with each task*/
var Tes{TASKS} >= 0; # Earliest Start
var Tef{TASKS} >= 0; # Earliest Finish
var Tls{TASKS} >= 0; # Latest Start
var Tlf{TASKS} >= 0; # Latest Finish
var Tsl{TASKS} >= 0; # Slacks
/* Global finish time */
var Tf >= 0;
/* Minimize the global finish time and, secondarily, maximize slacks */
minimize ProjectFinish : card(TASKS)*Tf - sum {j in TASKS} Tsl[j];
/* Finish is the least upper bound on the finish time for all tasks */
s.t. Efnsh {j in TASKS} : Tef[j] <= Tf;
s.t. Lfnsh {j in TASKS} : Tlf[j] <= Tf;
/* Relationship between start and finish times for each task */
s.t. Estrt {j in TASKS} : Tef[j] = Tes[j] + dur[j];
s.t. Lstrt {j in TASKS} : Tlf[j] = Tls[j] + dur[j];
/* Slacks */
s.t. Slack {j in TASKS} : Tsl[j] = Tls[j] - Tes[j];
/* Task ordering */
s.t. Eordr {(i,j) in ARCS} : Tef[i] <= Tes[j];
s.t. Lordr {(j,k) in ARCS} : Tlf[j] <= Tls[k];
/* Compute Solution */
solve;
/* Print Report */
printf 'PROJECT LENGTH = %8g\n',Tf;
/* Critical Tasks are those with zero slack */
/* Rank-order tasks on the critical path by earliest start time */
param r{j in TASKS : Tsl[j] = 0} := sum{k in TASKS : Tsl[k] = 0}
if (Tes[k] <= Tes[j]) then 1;
printf '\nCRITICAL PATH\n';
printf ' TASK DUR Start Finish Description\n';
printf {k in 1..card(TASKS), j in TASKS : Tsl[j]=0 && k==r[j]}
'%6s %4g %8g %8g %-25s\n', j, dur[j], Tes[j], Tef[j], desc[j];
/* Noncritical Tasks have positive slack */
/* Rank-order tasks not on the critical path by earliest start time */
param s{j in TASKS : Tsl[j] > 0} := sum{k in TASKS : Tsl[k] = 0}
if (Tes[k] <= Tes[j]) then 1;
printf '\nNON-CRITICAL TASKS\n';
printf ' Earliest Earliest Latest Latest \n';
printf ' TASK DUR Start Finish Start Finish Slack Description\n';
printf {k in 1..card(TASKS), j in TASKS : Tsl[j] > 0 && k==s[j]}
'%6s %4g %8g %8g %8g %8g %8g %-25s\n',
j,dur[j],Tes[j],Tef[j],Tls[j],Tlf[j],Tsl[j],desc[j];
printf '\n';
end;
Overwriting ProjectCPM.mod
%%script glpsol -m ProjectCPM.mod -d /dev/stdin -y ProjectCPM.txt --out output
param : TASKS : dur desc :=
T01 2.0 'Installing the contruction site'
T02 16.0 'Terracing'
T03 9.0 'Constructing the foundations'
T04 8.0 'Access roads and other networks'
T05 10.0 'Erecting the basement'
T06 6.0 'Main floor'
T07 2.0 'Dividing up the changing rooms'
T08 2.0 'Electrifying the terraces'
T09 9.0 'Constructing the roof'
T10 5.0 'Lighting the stadium'
T11 3.0 'Installing the terraces'
T12 2.0 'Sealing the roof'
T13 1.0 'Finishing the changing rooms'
T14 7.0 'Constructing the ticket office'
T15 4.0 'Secondary access roads'
T16 3.0 'Means of signaling'
T17 9.0 'Lawn and sports accessories'
T18 1.0 'Handing over the building' ;
set ARCS :=
T01 T02
T02 T03
T02 T04
T02 T14
T03 T05
T04 T07
T04 T10
T04 T09
T04 T06
T04 T15
T05 T06
T06 T09
T06 T11
T06 T08
T07 T13
T08 T16
T09 T12
T11 T16
T12 T17
T14 T16
T14 T15
T17 T18 ;
end;
f = open('ProjectCPM.txt')
print f.read()
f.close()
PROJECT LENGTH = 64 CRITICAL PATH TASK DUR Start Finish Description T01 2 0 2 Installing the contruction site T02 16 2 18 Terracing T03 9 18 27 Constructing the foundations T05 10 27 37 Erecting the basement T06 6 37 43 Main floor T09 9 43 52 Constructing the roof T12 2 52 54 Sealing the roof T17 9 54 63 Lawn and sports accessories T18 1 63 64 Handing over the building NON-CRITICAL TASKS Earliest Earliest Latest Latest TASK DUR Start Finish Start Finish Slack Description T04 8 18 26 29 37 11 Access roads and other networks T07 2 26 28 61 63 35 Dividing up the changing rooms T10 5 26 31 59 64 33 Lighting the stadium T14 7 18 25 53 60 35 Constructing the ticket office T15 4 26 30 60 64 34 Secondary access roads T13 1 28 29 63 64 35 Finishing the changing rooms T08 2 43 45 59 61 16 Electrifying the terraces T11 3 43 46 58 61 15 Installing the terraces T16 3 46 49 61 64 15 Means of signaling
import networkx as nx
import matplotlib.pyplot as plt
%matplotlib inline
G=nx.Graph()
G.add_nodes_from(['T01','T02','T03','T04','T05','T06','T07','T08',\
'T09','T10','T11','T12','T13','T14','T15','T16','T18'])
G.add_edge('T01','T02')
G.add_edge('T02','T03')
G.add_edge('T02','T04')
G.add_edge('T02','T14')
G.add_edge('T03','T05')
G.add_edge('T04','T07')
G.add_edge('T04','T10')
G.add_edge('T04','T09')
G.add_edge('T04','T06')
G.add_edge('T04','T15')
G.add_edge('T05','T06')
G.add_edge('T06','T09')
G.add_edge('T06','T11')
G.add_edge('T06','T08')
G.add_edge('T07','T13')
G.add_edge('T08','T16')
G.add_edge('T09','T12')
G.add_edge('T11','T16')
G.add_edge('T12','T17')
G.add_edge('T14','T16')
G.add_edge('T14','T15')
G.add_edge('T17','T18') ;
nx.draw(G)
plt.show()
/Users/jeff/anaconda/lib/python2.7/site-packages/matplotlib/collections.py:650: FutureWarning: elementwise comparison failed; returning scalar instead, but in the future will perform elementwise comparison if self._edgecolors_original != str('face'): /Users/jeff/anaconda/lib/python2.7/site-packages/matplotlib/collections.py:590: FutureWarning: elementwise comparison failed; returning scalar instead, but in the future will perform elementwise comparison if self._edgecolors == str('face'):